Bathroom and WIR renovation, Ocean Reef

What we did

With the clients supplied plans and engineering, PCR Constructions worked closely with the clients to renovate their existing Ensuite and robe into a large modern space. This transformation took 6 weeks from start to finish and included:

  • Demolition of the existing ensuite
  • Prop existing roof frame while removing structural walls
  • Removal of external timber door access to compete a separate games room
  • Brick up external after removal of door frame
  • Install new brick work/ Nib wall and sliding door frame
  • Install new window frame
  • Install steel framework for larger walk-in robe
  • Install niche box for shower recess
  • Alter roof frame with new structural timbers
  • New plumbing for wall hung vanity
  • New plumbing layout for updated fixtures and fittings
  • Electrical work allowing for power inside the vanity
  • New cabinet and top
  • Waterproofing as per Australian standards
  • Installation of floor and walls tiles
  • Tile inserts for that great finish on the floor
  • Frameless shower screen on top of nib wall
  • Installation of new lights and exhaust fan
  • 900mm triple mirror shaver cabinet
  • Fixtures and fittings
  • Soffit ceiling and mirrored slider for further robe space